ITAC Assessment: TT0331
ITAC logo
ITAC Assessment: TT0331
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Mobile homes
NAICS 321991: Manufactured Home (Mobile Home) Manufacturing
SIC 2451: Mobile Homes
Sales Range $100
M
to 500
M
# of Employees 309
Plant Area 20,000
ft2
Annual Production 1,935
units
Production Hrs. Annual 2,000
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $77,110 903,840
kWh
Electricity Demand $49,860 3,752
kW-mo/yr
Electricity Fees $1,907 -
Natural Gas $42,293 3,788
MMBtu
Waste Disposal Costs
Water Usage $6,137 891
Tgal
Water Disposal $10,392 891
Tgal
TOTAL YEARLY COSTS $187,699
RECOMMENDED SAVINGS* $87,848 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $393 $60 $393
4,610
kWh
- - - -
02 3.4151: Minimize water usage $1,508 $400 - - - $560
-
Tgal
$948
-
Tgal
03 2.2437: Recover waste heat from equipment $2,170 $3,000 - - $2,170
-
MMBtu
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $256 $450 $256
3,000
kWh
- - - -
05 4.721: Initiate a program to acquire iso certification $4,661 $15,000 $3,097
36,301
kWh
- $1,564
-
MMBtu
- -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,685 $9,000 $2,491
29,200
kWh
$194
-
kW-mo/yr
- - -
07 2.9114: Use solar heat to make electricty $75,885 $312,848 $75,885
889,525
kWh
- - - -
08 2.7134: Use photocell controls $290 $1,300 $290
3,400
kWh
- - - -
TOTAL RECOMMENDED $87,848 $342,058 $82,412
966,036
kWh
$194
-
kW-mo/yr
$3,734
-
MMBtu
$560
-
Tgal
$948
-
Tgal
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs