ITAC Assessment: TT0326
ITAC logo
ITAC Assessment: TT0326
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Open coil and cartridge style heaters
NAICS 333994: Industrial Process Furnace and Oven Manufacturing
SIC 3567: Industrial Process Furnaces and Ovens
Sales Range $10
M
to 50
M
# of Employees 225
Plant Area 420,000
ft2
Annual Production 900,000
pieces
Production Hrs. Annual 5,070
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $186,466 2,435,420
kWh
Electricity Demand $98,348 8,527
kW-mo/yr
Electricity Fees $(-56,421.0) -
Natural Gas $50,557 4,253
MMBtu
LPG $12,000 329
MMBtu
Waste Disposal Costs
Water Usage $3,329 729
Tgal
Water Disposal $6,570 729
Tgal
TOTAL YEARLY COSTS $300,849
RECOMMENDED SAVINGS* $215,771 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,814 $870 $3,814
49,816
kWh
- - - -
02 2.7261: Install timers and/or thermostats $7,420 $1,800 - - - $7,420
-
MMBtu
-
03 2.7228: Avoid introducing hot, humid, or dirty air into hvac system $2,701 $2,400 $2,701
35,287
kWh
- - - -
04 2.2511: Insulate bare equipment $3,234 $3,600 - - - $3,234
-
MMBtu
-
05 2.3212: Optimize plant power factor $2,637 $3,000 - - $2,637 - -
06 4.721: Initiate a program to acquire iso certification $8,775 $15,000 $6,899
90,084
kWh
- - $1,876
-
MMBtu
-
07 4.212: Adopt in-house material generation $50,975 $110,000 $(-2,025.0)
(-26,450)
kWh
- - - $53,000
08 2.7135: Install occupancy sensors $1,871 $4,200 $1,871
24,440
kWh
- - - -
09 2.9113: Use solar heat for heat $87,059 $375,030 $87,059
1,137,130
kWh
- - - -
10 3.1191: Change procedures / equipment / operating conditions $47,285 $724,290 $43,364
566,400
kWh
$3,921
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $215,771 $1,240,190 $143,683
1,876,708
kWh
$3,921
-
kW-mo/yr
$2,637 $12,530
-
MMBtu
$53,000
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs