Assessment Year | 2024 |
---|---|
Principal Product | Porcelain tile |
NAICS | 327120: Clay Building Material and Refractories Manufacturing |
SIC | 3253: Ceramic Wall and Floor Tile |
Sales Range | $10 M to 50M |
# of Employees | 178 |
Plant Area |
926,000
ft2
|
Annual Production | 3,650,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,249,965 | 16,408,800 |
kWh
|
$0.076 | |
Electricity Demand | $634,909 | 43,870 |
kW-mo/yr
|
$14.47 | |
Electricity Fees | $(-297,376.0) | - |
|
- | |
Natural Gas | $834,616 | 259,600 |
MMBtu
|
$3.22 | |
Waste Disposal Costs | |||||
Water Usage | $108,280 | 11,390 |
Tgal
|
$9.51 | |
Water Disposal | $148,368 | 11,390 |
Tgal
|
$13.03 | |
TOTAL YEARLY COSTS | $2,678,762 | ||||
RECOMMENDED SAVINGS* | $1,659,354 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $1,156,718 | $75,000 | - | - | $1,156,718 | - | - | - | |
02 | 2.9114: Use solar heat to make electricty | $259,778 | $1,375,785 |
$259,778
3,382,521
kWh
|
- | - | - | - | - | |
03 | 2.8114: Change rate schedules or other changes in utility service | $147,843 | $200,000 | - | - | $147,843 | - | - | - | |
04 | 3.4155: Meter waste water | $22,342 | $10,000 | - | - | - | - |
$22,342
-
Tgal
|
- | |
05 | 2.7225: Close outdoor air dampers during warm-up / cool-down periods | $18,330 | $3,200 | - | - | - | - | - | $18,330 | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $17,400 | $10,380 |
$13,828
180,057
kWh
|
$3,572
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.6218: Turn off equipment when not in use | $11,283 | $30 | - | - | - |
$11,283
-
MMBtu
|
- | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,806 | $12,000 |
$10,806
140,700
kWh
|
- | - | - | - | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,504 | $60 |
$7,504
97,709
kWh
|
- | - | - | - | - | |
10 | 2.2437: Recover waste heat from equipment | $5,587 | $1,500 | - | - | - |
$5,587
-
MMBtu
|
- | - | |
11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,763 | $1,345 |
$1,763
22,968
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $1,659,354 | $1,689,300 |
$293,679
3,823,955
kWh
|
$3,572
-
kW-mo/yr
|
$1,304,561 |
$16,870
-
MMBtu
|
$22,342
-
Tgal
|
$18,330 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs