Assessment Year | 2024 |
---|---|
Principal Product | Breads and buns |
NAICS | 311812: Commercial Bakeries |
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $100 M to 500M |
# of Employees | 235 |
Plant Area |
232,000
ft2
|
Annual Production | 75,250,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $517,632 | 6,162,654 |
kWh
|
$0.084 | |
Electricity Demand | $169,512 | 10,917 |
kW-mo/yr
|
$15.53 | |
Electricity Fees | $(-46,138.0) | - |
|
- | |
Natural Gas | $359,175 | 51,154 |
MMBtu
|
$7.02 | |
Waste Disposal Costs | |||||
Water Usage | $69,824 | 7,160 |
Tgal
|
$9.75 | |
Water Disposal | $85,450 | 7,160 |
Tgal
|
$11.94 | |
TOTAL YEARLY COSTS | $1,155,455 | ||||
RECOMMENDED SAVINGS* | $64,372 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $25,939 | $3,600 |
$20,489
243,923
kWh
|
$5,450
-
kW-mo/yr
|
- | - | - | |
02 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $10,414 | $17,000 | - | - | - | - | $10,414 | |
03 | 2.2437: Recover waste heat from equipment | $9,068 | $12,500 | - | - | - |
$9,068
-
MMBtu
|
- | |
04 | 2.3212: Optimize plant power factor | $7,227 | $9,500 | - | - | $7,227 | - | - | |
05 | 2.7135: Install occupancy sensors | $6,590 | $2,200 |
$5,087
60,565
kWh
|
$1,503
-
kW-mo/yr
|
- | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,799 | $60 |
$3,796
45,192
kWh
|
$1,003
-
kW-mo/yr
|
- | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $335 | $75 |
$335
3,994
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $64,372 | $44,935 |
$29,707
353,674
kWh
|
$7,956
-
kW-mo/yr
|
$7,227 |
$9,068
-
MMBtu
|
$10,414 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs