ITAC Assessment: TT0306
ITAC logo
ITAC Assessment: TT0306
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Metal Fabrication
NAICS 332119: Metal Crown, Closure, and Other Metal Stamping (except Automotive)
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 53
Plant Area 125,000
ft2
Annual Production 17,483,221
units
Production Hrs. Annual 4,550
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $63,705 663,500
kWh
Electricity Demand $21,242 2,182
kW-mo/yr
Natural Gas $14,256 1,349
MMBtu
Waste Disposal Costs
Water Usage $4,692 281
Tgal
Water Disposal $2,224 281
Tgal
TOTAL YEARLY COSTS $106,119
RECOMMENDED SAVINGS* $20,968 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Usage Savings Water Disposal Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,784 $3,840 $3,774
39,312
kWh
$1,010
-
kW-mo/yr
- - -
02 2.8121: Apply for tax-free status for energy purchases $4,348 - - - - - $4,348
03 3.4113: Treat and reuse rinse waters $3,460 $1,590 - - $2,347
-
Tgal
$1,113
-
Tgal
-
04 2.6212: Turn off equipment during breaks, reduce operating time $3,347 $2,600 $3,347
34,866
kWh
- - - -
05 2.7135: Install occupancy sensors $1,321 $1,560 $1,321
13,764
kWh
- - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $917 $113 $917
9,555
kWh
- - - -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $828 $840 $828
8,620
kWh
- - - -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $819 $785 $819
8,529
kWh
- - - -
09 2.7224: Reduce space conditioning during non-working hours $650 $100 $650
6,773
kWh
- - - -
10 2.6212: Turn off equipment during breaks, reduce operating time $494 $1,400 $494
5,148
kWh
- - - -
TOTAL RECOMMENDED $20,968 $12,828 $12,150
126,567
kWh
$1,010
-
kW-mo/yr
$2,347
-
Tgal
$1,113
-
Tgal
$4,348
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Usage Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs