Assessment Year | 2023 |
---|---|
Principal Product | Engine Transmissions |
NAICS | 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
264,300
ft2
|
Annual Production | 1,100,000
units
|
Production Hrs. Annual | 6,900
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $642,018 | 9,516,030 |
kWh
|
$0.067 | |
Electricity Demand | $253,025 | 19,692 |
kW-mo/yr
|
$12.85 | |
Natural Gas | $34,262 | 3,194 |
MMBtu
|
$10.73 | |
Waste Disposal Costs | |||||
Water Usage | $6,195 | 2,668 |
Tgal
|
$2.32 | |
Water Disposal | $34,272 | 2,668 |
Tgal
|
$12.85 | |
TOTAL YEARLY COSTS | $969,772 | ||||
RECOMMENDED SAVINGS* | $73,624 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $31,746 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.6192: Use a less expensive method of waste removal | $28,974 | $250 | - | - |
$(-87.0)
-
MMBtu
|
$(-412.0) | $29,473 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,314 | $15,941 |
$11,400
168,899
kWh
|
$2,915
-
kW-mo/yr
|
- | - | - | |
03 | 2.7229: Air condition only space necessary | $8,884 | $18,000 |
$2,739
40,579
kWh
|
- |
$6,145
-
MMBtu
|
- | - | |
04 | 2.8114: Change rate schedules or other changes in utility service | $6,900 | $600 | - | - | - | - | $6,900 | |
05 | 2.4221: Install compressor air intakes in coolest locations | $6,004 | $4,240 |
$4,527
67,060
kWh
|
$1,477
-
kW-mo/yr
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,057 | $2,190 |
$5,057
74,918
kWh
|
- | - | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,223 | $4,750 |
$2,223
32,936
kWh
|
- | - | - | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,268 | $50 |
$1,268
18,780
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $73,624 | $46,021 |
$27,213
403,172
kWh
|
$4,392
-
kW-mo/yr
|
$6,058
-
MMBtu
|
$(-412.0) | $36,373 | ||
TOTAL IMPLEMENTED | $31,746 | $40,931 |
$22,686
336,112
kWh
|
$2,915
-
kW-mo/yr
|
$6,145
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs