ITAC Assessment: TT0279
ITAC logo
ITAC Assessment: TT0279
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Marine Drives, Transoms, & Engines
NAICS 333618: Other Engine Equipment Manufacturing
SIC 3519: Internal Combustion Engines, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area 221,760
ft2
Annual Production 6,500
units
Production Hrs. Annual 4,200
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $357,557 5,419,200
kWh
Electricity Demand $240,338 17,306
kW-mo/yr
Natural Gas $112,430 12,906
MMBtu
Waste Disposal Costs
Water Usage $11,185 2,683
Tgal
Water Disposal $16,013 2,683
Tgal
TOTAL YEARLY COSTS $737,523
RECOMMENDED SAVINGS* $70,746 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $43,670

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4239: Eliminate or reduce compressed air usage $43,670 $43,750 $43,670
661,665
kWh
-
02 2.9114: Use solar heat to make electricty $12,173 $63,875 $12,173
184,442
kWh
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,514 $12,000 $4,064
61,572
kWh
$2,450
-
kW-mo/yr
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,957 $250 $5,957
90,255
kWh
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,432 $4,000 $2,432
36,841
kWh
-
TOTAL RECOMMENDED $70,746 $123,875 $68,296
1,034,775
kWh
$2,450
-
kW-mo/yr
TOTAL IMPLEMENTED $43,670 $43,750 $43,670
661,665
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs