Assessment Year | 2022 |
---|---|
Principal Product | Fuel and Oil Filtration Products |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 414 |
Plant Area |
338,958
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 5,760
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $238,834 | 3,698,400 |
kWh
|
$0.065 | |
Electricity Demand | $97,853 | 6,792 |
kW-mo/yr
|
$14.41 | |
Natural Gas | $56,511 | 5,584 |
MMBtu
|
$10.12 | |
LPG | $3,151 | 95 |
MMBtu
|
$33.17 | |
Waste Disposal Costs | |||||
Water Usage | $5,389 | 1,969 |
Tgal
|
$2.74 | |
Water Disposal | $5,420 | 1,969 |
Tgal
|
$2.75 | |
TOTAL YEARLY COSTS | $407,158 | ||||
RECOMMENDED SAVINGS* | $71,406 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $47,871 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,020 | $107,478 |
$21,038
325,669
kWh
|
$2,982
-
kW-mo/yr
|
- | - | - | |
02 | 2.6222: Use drying oven (batch type) on alternate days or other optimum schedule to run equipment with full loads | $14,885 | $400 |
$938
14,524
kWh
|
- |
$13,947
-
MMBtu
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,152 | $1,500 |
$8,781
135,929
kWh
|
$3,371
-
kW-mo/yr
|
- | - | - | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $5,912 | $18,000 |
$4,505
69,732
kWh
|
$547
-
kW-mo/yr
|
$860
-
MMBtu
|
- | - | |
05 | 2.7261: Install timers and/or thermostats | $4,507 | $150 |
$2,921
45,219
kWh
|
$(-72.0)
-
kW-mo/yr
|
$1,658
-
MMBtu
|
- | - | |
06 | 2.6218: Turn off equipment when not in use | $4,143 | - |
$4,143
62,128
kWh
|
- | - | - | - | |
07 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $3,425 | - |
$(-506.0)
(-7,833)
kWh
|
- | - |
$3,151
-
MMBtu
|
$780 | |
08 | 2.4237: Substitute compressed air cooling with water or air cooling | $2,362 | $2,736 |
$2,362
36,555
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $71,406 | $130,264 |
$44,182
681,923
kWh
|
$6,828
-
kW-mo/yr
|
$16,465
-
MMBtu
|
$3,151
-
MMBtu
|
$780 | ||
TOTAL IMPLEMENTED | $47,871 | $129,714 |
$36,180
560,052
kWh
|
$6,900
-
kW-mo/yr
|
$860
-
MMBtu
|
$3,151
-
MMBtu
|
$780 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs