| Assessment Year | 2022 |
|---|---|
| Principal Product | Hydraulic Motors and Transmissions |
| NAICS | 333996: Fluid Power Pump and Motor Manufacturing |
| SIC | 3594: Fluid Power Pumps and Motors |
| Sales Range | $100 M to 500M |
| # of Employees | 448 |
| Plant Area |
250,000
ft2
|
| Annual Production | 150,000
units
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,308,258 | 18,860,400 |
kWh
|
$0.069 |
| Electricity Demand | $475,215 | 39,043 |
kW-mo/yr
|
$12.17 |
| Natural Gas | $40,332 | 17,096 |
MMBtu
|
$2.36 |
| TOTAL YEARLY COSTS | $1,823,805 | |||
| RECOMMENDED SAVINGS* | $78,386 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $18,121 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $32,630 | $34,500 | - | - | $32,630 | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,633 | $2,905 |
$14,633
210,850
kWh
|
- | - | - | |
| 03 | 4.424: Improve space comfort conditioning | $11,751 | $28,120 |
$11,299
162,805
kWh
|
$452
-
kW-mo/yr
|
- | - | |
| 04 | 2.9114: Use solar heat to make electricty | $8,032 | $30,830 |
$8,032
115,739
kWh
|
- | - | - | |
| 05 | 2.7224: Reduce space conditioning during non-working hours | $5,126 | $50 |
$5,126
73,863
kWh
|
- | - | - | |
| 06 | 2.7229: Air condition only space necessary | $3,488 | $9,000 |
$1,228
17,584
kWh
|
- | - |
$2,260
-
MMBtu
|
|
| 07 | 2.2437: Recover waste heat from equipment | $1,643 | $2,500 | - | - | - |
$1,643
-
MMBtu
|
|
| 08 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,083 | $500 |
$1,083
15,607
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $78,386 | $108,405 |
$41,401
596,448
kWh
|
$452
-
kW-mo/yr
|
$32,630 |
$3,903
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $18,121 | $11,905 |
$15,861
228,434
kWh
|
- | - |
$2,260
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs