| Assessment Year | 2022 |
|---|---|
| Principal Product | Exterior Automotive Mirrors |
| NAICS | 336111: Automobile Manufacturing |
| SIC | 3711: Motor Vehicles and Passenger Car Bodies |
| Sales Range | $100 M to 500M |
| # of Employees | 650 |
| Plant Area |
310,000
ft2
|
| Annual Production | 32,825,809
units
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $673,037 | 15,873,707 |
kWh
|
$0.042 | |
| Electricity Demand | $329,942 | 27,282 |
kW-mo/yr
|
$12.09 | |
| Natural Gas | $513,573 | 49,773 |
MMBtu
|
$10.32 | |
| Waste Disposal Costs | |||||
| Water Usage | $41,457 | 10,533 |
Tgal
|
$3.94 | |
| Water Disposal | $64,047 | 10,533 |
Tgal
|
$6.08 | |
| TOTAL YEARLY COSTS | $1,622,056 | ||||
| RECOMMENDED SAVINGS* | $328,993 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $72,599 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $197,305 | $1,241,200 |
$152,425
3,594,939
kWh
|
$62,094
-
kW-mo/yr
|
$(-17,214.0)
-
MMBtu
|
- | |
| 02 | 2.6212: Turn off equipment during breaks, reduce operating time | $65,016 | $5,000 | - | - |
$65,016
-
MMBtu
|
- | |
| 03 | 2.2511: Insulate bare equipment | $51,693 | $8,551 | - | - |
$51,693
-
MMBtu
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,155 | $2,860 |
$6,155
145,165
kWh
|
- | - | - | |
| 05 | 2.6212: Turn off equipment during breaks, reduce operating time | $3,192 | $2,000 | - |
$3,192
-
kW-mo/yr
|
- | - | |
| 06 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,707 | $400 | - | - | - |
$1,707
-
Tgal
|
|
| 07 | 2.2511: Insulate bare equipment | $1,084 | $428 | - | - |
$1,084
-
MMBtu
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,072 | $1,926 |
$762
17,976
kWh
|
$310
-
kW-mo/yr
|
- | - | |
| 09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $780 | $2,250 |
$551
13,007
kWh
|
$229
-
kW-mo/yr
|
- | - | |
| 10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $633 | $1,500 |
$447
10,537
kWh
|
$186
-
kW-mo/yr
|
- | - | |
| 11 | 2.6212: Turn off equipment during breaks, reduce operating time | $356 | $700 |
$356
8,400
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $328,993 | $1,266,815 |
$160,696
3,790,024
kWh
|
$66,011
-
kW-mo/yr
|
$100,579
-
MMBtu
|
$1,707
-
Tgal
|
||
| TOTAL IMPLEMENTED | $72,599 | $10,486 |
$7,273
171,541
kWh
|
$310
-
kW-mo/yr
|
$65,016
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs