Assessment Year | 2022 |
---|---|
Principal Product | Manufactured Metal Products |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
57,900
ft2
|
Annual Production | 2,000
units
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $185,704 | 4,265,912 |
kWh
|
$0.044 |
Electricity Demand | $164,462 | 12,936 |
kW-mo/yr
|
$12.71 |
Natural Gas | $96,173 | 7,875 |
MMBtu
|
$12.21 |
TOTAL YEARLY COSTS | $446,339 | |||
RECOMMENDED SAVINGS* | $49,380 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7242: Change zone reheat coils to variable air volume boxes | $24,682 | $2,000 |
$17,625
405,168
kWh
|
$7,058
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,069 | $25,000 |
$3,366
77,377
kWh
|
$5,703
-
kW-mo/yr
|
- | - | |
03 | 2.3212: Optimize plant power factor | $6,223 | $27,500 | - | - | $6,223 | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,847 | $3,500 |
$3,193
73,366
kWh
|
$655
-
kW-mo/yr
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,648 | $2,500 |
$2,605
59,874
kWh
|
$1,044
-
kW-mo/yr
|
- | - | |
06 | 2.2437: Recover waste heat from equipment | $1,911 | $11,000 | - | - | - |
$1,911
-
MMBtu
|
|
TOTAL RECOMMENDED | $49,380 | $71,500 |
$26,788
615,784
kWh
|
$14,459
-
kW-mo/yr
|
$6,223 |
$1,911
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs