ITAC Assessment: TT0254
ITAC logo
ITAC Assessment: TT0254
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Automotive glass: windshields, side glass and rear glass
NAICS 327215: Glass Product Manufacturing Made of Purchased Glass
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area 618,000
ft2
Annual Production 17,000
ton
Production Hrs. Annual 8,760
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,790,909 50,439,898
kWh
Electricity Demand $1,196,970 102,869
kW-mo/yr
Electricity Fees $2,620,484 -
Natural Gas $512,176 142,820
MMBtu
Waste Disposal Costs
Water Usage $158,207 37,452
Tgal
Water Disposal $286,842 37,452
Tgal
TOTAL YEARLY COSTS $6,565,588
RECOMMENDED SAVINGS* $199,063 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $132,788 $431,774 $90,430
2,547,325
kWh
$42,358
-
kW-mo/yr
- -
02 2.3212: Optimize plant power factor $42,725 $52,500 - - $42,725 -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,052 $6,750 $5,131
144,540
kWh
$1,921
-
kW-mo/yr
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,875 $4,500 $6,875
193,662
kWh
- - -
05 2.6218: Turn off equipment when not in use $7,171 $300 $6,787
191,167
kWh
$384
-
kW-mo/yr
- -
06 2.1121: Use insulation in furnaces to facilitate heating / cooling $2,452 $1,923 - - - $2,452
-
MMBtu
TOTAL RECOMMENDED $199,063 $497,747 $109,223
3,076,694
kWh
$44,663
-
kW-mo/yr
$42,725 $2,452
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs