Assessment Year | 2020 |
---|---|
Principal Product | Sand |
NAICS | 212322: Industrial Sand Mining |
SIC | 1446: Industrial Sand |
Sales Range | $50 M to 100M |
# of Employees | 31 |
Plant Area |
100,000
ft2
|
Annual Production | 500,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $902,650 | 17,750,934 |
kWh
|
$0.051 |
Electricity Demand | $689,050 | 56,452 |
kW-mo/yr
|
$12.21 |
Natural Gas | $345,016 | 89,615 |
MMBtu
|
$3.85 |
Fuel Oil #2 | $250,100 | 14,248 |
MMBtu
|
$17.55 |
TOTAL YEARLY COSTS | $2,186,816 | |||
RECOMMENDED SAVINGS* | $87,829 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $67,316 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1113: Reduce combustion air flow to optimum | $28,385 | $3,500 | - | - |
$28,385
-
MMBtu
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $19,091 | $75,890 |
$9,674
190,434
kWh
|
$4,712
-
kW-mo/yr
|
- | - | $4,705 | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,222 | $25,000 |
$13,222
260,275
kWh
|
- | - | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $10,965 | $22,780 |
$10,965
215,850
kWh
|
- | - | - | - | |
05 | 2.8226: Increase efficiency of trucks | $7,291 | $24,565 | - | - | - |
$7,291
-
MMBtu
|
- | |
06 | 2.4323: Use optimum size and capacity equipment | $6,836 | $1,500 |
$6,836
134,567
kWh
|
- | - | - | - | |
07 | 2.2136: Install / repair insulation on steam lines | $1,527 | $350 | - | - |
$1,527
-
MMBtu
|
- | - | |
08 | 2.6218: Turn off equipment when not in use | $511 | $40 |
$511
10,066
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $87,829 | $153,625 |
$41,209
811,192
kWh
|
$4,712
-
kW-mo/yr
|
$29,912
-
MMBtu
|
$7,291
-
MMBtu
|
$4,705 | ||
TOTAL IMPLEMENTED | $67,316 | $104,060 |
$27,987
550,917
kWh
|
$4,712
-
kW-mo/yr
|
$29,912
-
MMBtu
|
- | $4,705 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs