ITAC Assessment: TT0236
ITAC logo
ITAC Assessment: TT0236
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Engine Valves
NAICS 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $50
M
to 100
M
# of Employees 235
Plant Area 175,000
ft2
Annual Production 53,000,000
pieces
Production Hrs. Annual 8,064
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $921,502 25,312,612
kWh
Electricity Demand $632,315 91,316
kW-mo/yr
Electricity Fees $78,000 -
Natural Gas $194,739 21,962
MMBtu
Waste Disposal Costs
Water Usage $39,024 2,069,700
Tgal
Water Disposal $49,500 2,595
Tgal
TOTAL YEARLY COSTS $1,915,080
RECOMMENDED SAVINGS* $105,579 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $48,879

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Usage Savings
01 2.3212: Optimize plant power factor $28,173 $90,000 - - $28,173 -
02 4.212: Adopt in-house material generation $28,629 $16,000 $(-202.5)
(-5,564)
kWh
$(-57.3)
-
kW-mo/yr
$28,889 -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $20,250 $128,083 $15,165
416,620
kWh
$5,085
-
kW-mo/yr
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,754 $2,700 $6,498
178,507
kWh
$2,256
-
kW-mo/yr
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,447 $15,750 $6,370
175,000
kWh
$2,077
-
kW-mo/yr
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,574 $40 $6,574
180,600
kWh
- - -
07 2.5195: Change product design to reduce energy requirements $1,908 $500 $1,908
52,429
kWh
- - -
08 3.4116: Meter recycled water (to reduce sewer charges) $1,653 $2,150 - - - $1,653
-
Tgal
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $984 $1,500 $984
27,025
kWh
- - -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $206 $450 $153
4,210
kWh
$53
-
kW-mo/yr
- -
TOTAL RECOMMENDED $105,579 $257,173 $37,450
1,028,827
kWh
$9,414
-
kW-mo/yr
$57,062 $1,653
-
Tgal
TOTAL IMPLEMENTED $48,879 $144,083 $14,963
411,056
kWh
$5,028
-
kW-mo/yr
$28,889 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs