Assessment Year | 2019 |
---|---|
Principal Product | Medium Voltage Switchgear |
NAICS | 335311: Power, Distribution, and Specialty Transformer Manufacturing |
SIC | 3612: Power, Distribution, and Specialty Transformers |
Sales Range | $100 M to 500M |
# of Employees | 300 |
Plant Area |
200,000
ft2
|
Annual Production | 6,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $264,189 | 4,258,000 |
kWh
|
$0.062 | |
Electricity Demand | $121,684 | 11,184 |
kW-mo/yr
|
$10.88 | |
Natural Gas | $68,637 | 12,155 |
MMBtu
|
$5.65 | |
Waste Disposal Costs | |||||
Water Usage | $4 | 264 |
Tgal
|
$0.017 | |
Water Disposal | $4 | 0 |
Tgal
|
$16.86 | |
Solid Waste (non-haz) | $90,399 | 652,800 |
lb
|
$0.14 | |
TOTAL YEARLY COSTS | $544,918 | ||||
RECOMMENDED SAVINGS* | $91,480 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $11,701 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $73,127 | $4,450 | - | - | - |
$63,279
-
lb
|
$(-13,000.0) | - | $22,848 | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,143 | $2,500 | - |
$(-25,958.0)
-
kW-mo/yr
|
$31,101 | - | - | - | - | |
03 | 3.6192: Use a less expensive method of waste removal | $4,828 | $5,000 | - | - | - |
$9,040
-
lb
|
$(-4,212.0) | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,227 | $2,000 |
$3,299
53,213
kWh
|
$928
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.4224: Upgrade controls on compressors | $2,646 | $2,000 |
$2,646
42,678
kWh
|
- | - | - | - | - | - | |
06 | 2.7224: Reduce space conditioning during non-working hours | $1,110 | $550 |
$1,110
17,911
kWh
|
- | - | - | - | - | - | |
07 | 3.6192: Use a less expensive method of waste removal | $399 | $750 | - | - | - |
$4,520
-
lb
|
$(-1,300.0) | $(-2,821.0) | - | |
TOTAL RECOMMENDED | $91,480 | $17,250 |
$7,055
113,802
kWh
|
$(-25,030.0)
-
kW-mo/yr
|
$31,101 |
$76,839
-
lb
|
$(-18,512.0) | $(-2,821.0) | $22,848 | ||
TOTAL IMPLEMENTED | $11,701 | $9,000 |
$5,945
95,891
kWh
|
$928
-
kW-mo/yr
|
- |
$9,040
-
lb
|
$(-4,212.0) | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs