| Assessment Year | 2019 |
|---|---|
| Principal Product | Superconducting Magnets |
| NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
| SIC | 3829: Measuring and Controlling Devices, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 48 |
| Plant Area |
29,880
ft2
|
| Annual Production | 120
units
|
| Production Hrs. Annual | 2,088
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $56,049 | 564,660 |
kWh
|
$0.099 | |
| Electricity Demand | $8,462 | 1,632 |
kW-mo/yr
|
$5.19 | |
| Natural Gas | $4,046 | 370 |
MMBtu
|
$10.94 | |
| Waste Disposal Costs | |||||
| Water Usage | $2,492 | 356,000 |
Tgal
|
$0.007 | |
| Water Disposal | $4,078 | 356 |
Tgal
|
$11.46 | |
| TOTAL YEARLY COSTS | $75,127 | ||||
| RECOMMENDED SAVINGS* | $18,627 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $11,132 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,132 | $36,211 |
$9,069
91,313
kWh
|
$2,063
-
kW-mo/yr
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $4,069 | $2,280 |
$210
2,118
kWh
|
- |
$3,859
-
MMBtu
|
|
| 03 | 2.2437: Recover waste heat from equipment | $1,958 | $7,400 |
$1,827
18,396
kWh
|
$131
-
kW-mo/yr
|
- | |
| 04 | 2.6218: Turn off equipment when not in use | $1,435 | $30 |
$1,435
14,454
kWh
|
- | - | |
| 05 | 2.2511: Insulate bare equipment | $33 | $80 | - | - |
$33
-
MMBtu
|
|
| TOTAL RECOMMENDED | $18,627 | $46,001 |
$12,541
126,281
kWh
|
$2,194
-
kW-mo/yr
|
$3,892
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $11,132 | $36,211 |
$9,069
91,313
kWh
|
$2,063
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs