Assessment Year | 2019 |
---|---|
Principal Product | Plastic Injection |
NAICS | 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
Sales Range | $50 M to 100M |
# of Employees | 330 |
Plant Area |
170,000
ft2
|
Annual Production | 1,500,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $933,677 | 14,683,200 |
kWh
|
$0.064 | |
Electricity Demand | $485,431 | 32,691 |
kW-mo/yr
|
$14.85 | |
Natural Gas | $107,708 | 13,797 |
MMBtu
|
$7.81 | |
Waste Disposal Costs | |||||
Water Usage | $4,125 | 754 |
Tgal
|
$5.47 | |
Water Disposal | $5,609 | 754 |
Tgal
|
$7.44 | |
TOTAL YEARLY COSTS | $1,536,550 | ||||
RECOMMENDED SAVINGS* | $121,375 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $79,045 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $36,872 | $88,116 |
$24,845
390,658
kWh
|
$12,027
-
kW-mo/yr
|
- | - | - | |
02 | 2.3212: Optimize plant power factor | $34,064 | $64,000 | - |
$34,064
-
kW-mo/yr
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $18,304 | $80 |
$18,304
287,791
kWh
|
- | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,995 | $6,300 |
$11,585
182,160
kWh
|
$5,410
-
kW-mo/yr
|
- | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,534 | $60 |
$4,704
73,954
kWh
|
$1,830
-
kW-mo/yr
|
- | - | - | |
06 | 2.2437: Recover waste heat from equipment | $5,115 | $15,000 | - | - |
$5,115
-
MMBtu
|
- | - | |
07 | 2.8114: Change rate schedules or other changes in utility service | $1,624 | $2,150 | - | - | - |
$1,624
-
Tgal
|
- | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,527 | $945 |
$1,527
24,008
kWh
|
- | - | - | - | |
09 | 2.8118: Check for accuracy of utility / power meters | $340 | $60 | - | - | - | - | $340 | |
TOTAL RECOMMENDED | $121,375 | $176,711 |
$60,965
958,571
kWh
|
$53,331
-
kW-mo/yr
|
$5,115
-
MMBtu
|
$1,624
-
Tgal
|
$340 | ||
TOTAL IMPLEMENTED | $79,045 | $94,616 |
$59,438
934,563
kWh
|
$19,267
-
kW-mo/yr
|
- | - | $340 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs