| Assessment Year | 2019 |
|---|---|
| Principal Product | Airbag Modules and Textiles |
| NAICS | 336360: Motor Vehicle Seating and Interior Trim Manufacturing |
| SIC | 2295: Coated Fabrics, Not Rubberized |
| Sales Range | $100 M to 500M |
| # of Employees | 150 |
| Plant Area |
280,000
ft2
|
| Annual Production | 25,158,054
units
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $838,532 | 15,568,725 |
kWh
|
$0.054 | |
| Electricity Demand | $434,208 | 30,578 |
kW-mo/yr
|
$14.20 | |
| Electricity Fees | $34,907 | - |
|
- | |
| Natural Gas | $216,573 | 26,686 |
MMBtu
|
$8.12 | |
| Waste Disposal Costs | |||||
| Water Usage | $65,390 | 18,800 |
Tgal
|
$3.48 | |
| Water Disposal | $132,681 | 12,400 |
Tgal
|
$10.70 | |
| TOTAL YEARLY COSTS | $1,722,291 | ||||
| RECOMMENDED SAVINGS* | $44,366 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $22,915 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $21,451 | $2,000 | - | - | - | - | $21,451 | |
| 02 | 2.3212: Optimize plant power factor | $14,507 | $20,000 | - | - | $14,507 | - | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,494 | $3,750 |
$3,267
60,653
kWh
|
$1,227
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.2136: Install / repair insulation on steam lines | $1,254 | $1,710 | - | - | - |
$1,254
-
MMBtu
|
- | |
| 05 | 2.6218: Turn off equipment when not in use | $1,220 | $20 |
$896
16,644
kWh
|
$324
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,054 | $3,559 |
$1,054
19,561
kWh
|
- | - | - | - | |
| 07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $386 | $1,530 |
$284
5,273
kWh
|
$102
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $44,366 | $32,569 |
$5,501
102,131
kWh
|
$1,653
-
kW-mo/yr
|
$14,507 |
$1,254
-
MMBtu
|
$21,451 | ||
| TOTAL IMPLEMENTED | $22,915 | $30,569 |
$5,501
102,131
kWh
|
$1,653
-
kW-mo/yr
|
$14,507 |
$1,254
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs