Assessment Year | 2018 |
---|---|
Principal Product | Cars |
NAICS | 336111: Automobile Manufacturing |
SIC | 3711: Motor Vehicles and Passenger Car Bodies |
Sales Range | greater than $500 M |
# of Employees | 6,500 |
Plant Area |
4,500,000
ft2
|
Annual Production | 315,000
units
|
Production Hrs. Annual | 8,064
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $5,739,791 | 215,054,000 |
kWh
|
$0.027 | |
Electricity Demand | $3,372,002 | 454,194 |
kW-mo/yr
|
$7.42 | |
Natural Gas | $2,466,613 | 803,743 |
MMBtu
|
$3.07 | |
Waste Disposal Costs | |||||
Water Usage | $730,738 | 326,952 |
Tgal
|
$2.24 | |
Water Disposal | $417,942 | 278,628 |
Tgal
|
$1.50 | |
TOTAL YEARLY COSTS | $12,727,086 | ||||
RECOMMENDED SAVINGS* | $326,729 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $145,597 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 2.7212: Install or upgrade insulation on hvac distribution systems | $76,685 | $250,172 |
$76,685
2,873,165
kWh
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $68,776 | $32,000 |
$48,642
1,822,464
kWh
|
$20,134
-
kW-mo/yr
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $68,707 | $330,000 |
$68,707
2,574,261
kWh
|
- | - | |
04 | 2.7212: Install or upgrade insulation on hvac distribution systems | $38,635 | $13,000 |
$38,635
1,447,545
kWh
|
- | - | |
05 | 3.4155: Meter waste water | $34,128 | $1,900 | - | - |
$34,128
-
Tgal
|
|
06 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $17,427 | $79,168 |
$17,427
652,938
kWh
|
- | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $9,248 | $34,845 |
$6,056
226,829
kWh
|
$3,192
-
kW-mo/yr
|
- | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,795 | $16,665 |
$4,451
166,690
kWh
|
$2,344
-
kW-mo/yr
|
- | |
09 | 2.4113: Install motor voltage controller on lightly loaded motors | $3,775 | $5,000 |
$2,390
89,547
kWh
|
$1,385
-
kW-mo/yr
|
- | |
10 | 2.7212: Install or upgrade insulation on hvac distribution systems | $2,270 | $1,720 |
$1,644
61,583
kWh
|
$626
-
kW-mo/yr
|
- | |
11 | 2.7135: Install occupancy sensors | $283 | $250 |
$283
10,591
kWh
|
- | - | |
TOTAL RECOMMENDED | $326,729 | $764,720 |
$264,920
9,925,613
kWh
|
$27,681
-
kW-mo/yr
|
$34,128
-
Tgal
|
||
TOTAL IMPLEMENTED | $145,597 | $52,150 |
$89,950
3,370,147
kWh
|
$21,519
-
kW-mo/yr
|
$34,128
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs