| Assessment Year | 2018 |
|---|---|
| Principal Product | Medical socks, Stockings, Castings, and Bandages |
| NAICS | 339113: Surgical Appliance and Supplies Manufacturing |
| SIC | 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies |
| Sales Range | $1 M to 5M |
| # of Employees | 175 |
| Plant Area |
260,000
ft2
|
| Annual Production | 4,560,000
lb
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $306,254 | 7,863,584 |
kWh
|
$0.039 | |
| Electricity Demand | $174,098 | 13,608 |
kW-mo/yr
|
$12.79 | |
| Natural Gas | $206,475 | 37,781 |
MMBtu
|
$5.47 | |
| Waste Disposal Costs | |||||
| Water Usage | $124,597 | 3,246,523 |
Tgal
|
$0.038 | |
| Water Disposal | $187,672 | 3,247 |
Tgal
|
$57.81 | |
| TOTAL YEARLY COSTS | $999,096 | ||||
| RECOMMENDED SAVINGS* | $41,952 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $4,089 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $24,976 | $33,750 |
$16,133
414,720
kWh
|
$8,843
-
kW-mo/yr
|
- | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,000 | $2,500 | - | - |
$6,000
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,089 | $400 |
$4,089
105,120
kWh
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $3,716 | $2,030 |
$3,716
95,514
kWh
|
- | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,732 | $2,250 |
$1,765
45,360
kWh
|
$967
-
kW-mo/yr
|
- | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $439 | $600 |
$283
7,272
kWh
|
$156
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $41,952 | $41,530 |
$25,986
667,986
kWh
|
$9,966
-
kW-mo/yr
|
$6,000
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $4,089 | $400 |
$4,089
105,120
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs