| Assessment Year | 2017 |
|---|---|
| Principal Product | sunscreen, mouth antiseptic |
| NAICS | 325412: Pharmaceutical Preparation Manufacturing |
| SIC | 2834: Pharmaceutical Preparations |
| Sales Range | $50 M to 100M |
| # of Employees | 190 |
| Plant Area |
120,000
ft2
|
| Annual Production | 8,600,000
units
|
| Production Hrs. Annual | 4,800
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $145,688 | 2,285,736 |
kWh
|
$0.064 | |
| Electricity Demand | $65,550 | 5,472 |
kW-mo/yr
|
$11.98 | |
| Natural Gas | $26,282 | 4,316 |
MMBtu
|
$6.09 | |
| Waste Disposal Costs | |||||
| Water Usage | $12,573 | 4,522,600 |
Tgal
|
$0.003 | |
| Water Disposal | $26,160 | 4,523 |
Tgal
|
$5.78 | |
| TOTAL YEARLY COSTS | $276,253 | ||||
| RECOMMENDED SAVINGS* | $29,959 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,040 | $34,731 |
$12,549
196,983
kWh
|
$491
-
kW-mo/yr
|
- | |
| 02 | 2.6218: Turn off equipment when not in use | $6,861 | $25 |
$6,861
107,712
kWh
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,250 | $3,050 |
$4,250
66,720
kWh
|
- | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,281 | $3,000 |
$2,232
35,040
kWh
|
$1,049
-
kW-mo/yr
|
- | |
| 05 | 4.812: Apply for investment incentives | $1,314 | $20 | - | - | $1,314 | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,213 | $94 |
$825
12,950
kWh
|
$388
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $29,959 | $40,920 |
$26,717
419,405
kWh
|
$1,928
-
kW-mo/yr
|
$1,314 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs