| Assessment Year | 2016 |
|---|---|
| Principal Product | Carpet |
| NAICS | 314110: Carpet and Rug Mills |
| SIC | 2273: Carpets and Rugs |
| Sales Range | $1 M to 5M |
| # of Employees | 200 |
| Plant Area |
215,000
ft2
|
| Annual Production | 800,000
units
|
| Production Hrs. Annual | 7,738
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $514,181 | 12,700,800 |
kWh
|
$0.040 |
| Electricity Demand | $416,012 | 38,664 |
kW-mo/yr
|
$10.76 |
| Natural Gas | $334,010 | 90,637 |
MMBtu
|
$3.69 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $20,901 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,530 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2622: Replace existing chiller with high efficiency model | $13,371 | $30,500 |
$18,994
468,977
kWh
|
$9,652
-
kW-mo/yr
|
- |
$(-13,675.0)
-
gal
|
$(-1,600.0) | |
| 02 | 2.2437: Recover waste heat from equipment | $2,212 | $1,500 | - | - |
$2,212
-
MMBtu
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,194 | $3,000 |
$2,194
54,166
kWh
|
- | - | - | - | |
| 04 | 2.4226: Use / purchase optimum sized compressor | $1,630 | $3,525 |
$1,630
40,238
kWh
|
- | - | - | - | |
| 05 | 2.2511: Insulate bare equipment | $1,494 | $130 |
$1,494
36,909
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $20,901 | $38,655 |
$24,312
600,290
kWh
|
$9,652
-
kW-mo/yr
|
$2,212
-
MMBtu
|
$(-13,675.0)
-
gal
|
$(-1,600.0) | ||
| TOTAL IMPLEMENTED | $7,530 | $8,155 |
$5,318
131,313
kWh
|
- |
$2,212
-
MMBtu
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs