| Assessment Year | 2015 |
|---|---|
| Principal Product | Carpet |
| NAICS | 314110: Carpet and Rug Mills |
| SIC | 2273: Carpets and Rugs |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
123,000
ft2
|
| Annual Production | 26,177,472
thousand feet
|
| Production Hrs. Annual | 4,800
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $202,965 | 2,826,000 |
kWh
|
$0.072 |
| Electricity Demand | $16,478 | 10,299 |
kW-mo/yr
|
$1.60 |
| Natural Gas | $337,476 | 61,478 |
MMBtu
|
$5.49 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $53,940 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,223 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2414: Use waste heat from hot flue gases to preheat | $31,925 | $52,507 | - | - |
$31,925
-
MMBtu
|
- | |
| 02 | 2.2135: Repair and eliminate steam leaks | $13,551 | $15,000 | - | - |
$12,407
-
MMBtu
|
$1,144
-
gal
|
|
| 03 | 2.2437: Recover waste heat from equipment | $2,241 | $10,000 | - | - |
$2,241
-
MMBtu
|
- | |
| 04 | 2.1213: Direct warmest air to combustion intake | $3,000 | $5,000 | - | - |
$3,000
-
MMBtu
|
- | |
| 05 | 2.2136: Install / repair insulation on steam lines | $1,769 | $1,651 | - | - |
$1,769
-
MMBtu
|
- | |
| 06 | 2.4235: Remove or close off unneeded compressed air lines | $1,454 | $13 |
$1,377
19,179
kWh
|
$77
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $53,940 | $84,171 |
$1,377
19,179
kWh
|
$77
-
kW-mo/yr
|
$51,342
-
MMBtu
|
$1,144
-
gal
|
||
| TOTAL IMPLEMENTED | $3,223 | $1,664 |
$1,377
19,179
kWh
|
$77
-
kW-mo/yr
|
$1,769
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs