ITAC Assessment: TT0156
ITAC logo
ITAC Assessment: TT0156
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Carpet
NAICS 314110: Carpet and Rug Mills
SIC 2273: Carpets and Rugs
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 123,000
ft2
Annual Production 26,177,472
thousand feet
Production Hrs. Annual 4,800
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $202,965 2,826,000
kWh
Electricity Demand $16,478 10,299
kW-mo/yr
Natural Gas $337,476 61,478
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $53,940 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,223

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings
01 2.2414: Use waste heat from hot flue gases to preheat $31,925 $52,507 - - $31,925
-
MMBtu
-
02 2.2135: Repair and eliminate steam leaks $13,551 $15,000 - - $12,407
-
MMBtu
$1,144
-
gal
03 2.2437: Recover waste heat from equipment $2,241 $10,000 - - $2,241
-
MMBtu
-
04 2.1213: Direct warmest air to combustion intake $3,000 $5,000 - - $3,000
-
MMBtu
-
05 2.2136: Install / repair insulation on steam lines $1,769 $1,651 - - $1,769
-
MMBtu
-
06 2.4235: Remove or close off unneeded compressed air lines $1,454 $13 $1,377
19,179
kWh
$77
-
kW-mo/yr
- -
TOTAL RECOMMENDED $53,940 $84,171 $1,377
19,179
kWh
$77
-
kW-mo/yr
$51,342
-
MMBtu
$1,144
-
gal
TOTAL IMPLEMENTED $3,223 $1,664 $1,377
19,179
kWh
$77
-
kW-mo/yr
$1,769
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs