Assessment Year | 2015 |
---|---|
Principal Product | Marine Power Systems |
NAICS | 333618: Other Engine Equipment Manufacturing |
SIC | 3519: Internal Combustion Engines, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 117 |
Plant Area |
213,260
ft2
|
Annual Production | 6,500
pieces
|
Production Hrs. Annual | 4,200
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $277,629 | 4,262,400 |
kWh
|
$0.065 |
Electricity Demand | $206,516 | 16,696 |
kW-mo/yr
|
$12.37 |
Natural Gas | $133,010 | 24,838 |
MMBtu
|
$5.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $56,911 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,151 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1133: Adjust burners for efficient operation | $12,531 | $1,500 | - | - |
$12,531
-
MMBtu
|
|
02 | 2.2511: Insulate bare equipment | $11,633 | $6,247 |
$11,633
178,969
kWh
|
- | - | |
03 | 2.2511: Insulate bare equipment | $3,904 | $740 |
$3,904
60,067
kWh
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,662 | $8,000 |
$2,376
36,554
kWh
|
$1,286
-
kW-mo/yr
|
- | |
05 | 2.4239: Eliminate or reduce compressed air usage | $8,830 | $1,514 |
$8,830
135,846
kWh
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,084 | $3,000 |
$2,649
40,758
kWh
|
$1,435
-
kW-mo/yr
|
- | |
07 | 2.6218: Turn off equipment when not in use | $10,606 | $2,440 |
$10,606
163,170
kWh
|
- | - | |
08 | 2.6218: Turn off equipment when not in use | $755 | $440 |
$755
11,613
kWh
|
- | - | |
09 | 2.7122: Disconnect ballasts | $275 | $90 |
$218
3,351
kWh
|
$57
-
kW-mo/yr
|
- | |
10 | 2.7135: Install occupancy sensors | $384 | $804 |
$384
5,906
kWh
|
- | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $247 | $1,200 |
$160
2,457
kWh
|
$87
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $56,911 | $25,975 |
$41,515
638,691
kWh
|
$2,865
-
kW-mo/yr
|
$12,531
-
MMBtu
|
||
TOTAL IMPLEMENTED | $24,151 | $8,958 |
$22,629
348,137
kWh
|
$1,522
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs