Assessment Year | 2014 |
---|---|
Principal Product | Residential Oven Racks |
NAICS | 331222: Steel Wire Drawing |
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
130,000
ft2
|
Annual Production | 4,992,000
pieces
|
Production Hrs. Annual | 5,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $254,137 | 3,969,600 |
kWh
|
$0.064 |
Electricity Demand | $130,911 | 10,330 |
kW-mo/yr
|
$12.67 |
Electricity Fees | $36,307 | - |
|
- |
Natural Gas | $126,258 | 23,004 |
MMBtu
|
$5.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,720 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,005 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,305 | $1,400 | - | - |
$2,305
-
MMBtu
|
|
02 | 2.2136: Install / repair insulation on steam lines | $299 | $596 | - | - |
$299
-
MMBtu
|
|
03 | 2.2136: Install / repair insulation on steam lines | $861 | $1,662 | - | - |
$861
-
MMBtu
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,651 | $3,000 |
$8,640
135,000
kWh
|
$3,011
-
kW-mo/yr
|
- | |
05 | 2.7122: Disconnect ballasts | $555 | $60 |
$437
6,833
kWh
|
$118
-
kW-mo/yr
|
- | |
06 | 2.7134: Use photocell controls | $49 | $45 |
$49
766
kWh
|
- | - | |
TOTAL RECOMMENDED | $15,720 | $6,763 |
$9,126
142,599
kWh
|
$3,129
-
kW-mo/yr
|
$3,465
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,005 | $4,445 |
$8,689
135,766
kWh
|
$3,011
-
kW-mo/yr
|
$2,305
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs