ITAC Assessment: TT0135
ITAC logo
ITAC Assessment: TT0135
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Aluminum Door Frames
NAICS 336370: Motor Vehicle Metal Stamping
SIC 3465: Automotive Stampings
Sales Range $100
M
to 500
M
# of Employees 297
Plant Area 256,000
ft2
Annual Production 760,000
pieces
Production Hrs. Annual 4,625
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $430,616 6,737,100
kWh
Electricity Demand $189,391 18,769
kW-mo/yr
Electricity Fees $15,934 -
Natural Gas $95,935 10,321
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,714 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $38,363

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $4,394 $100 $3,341
52,202
kWh
$1,053
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,172 $3,000 $1,651
25,803
kWh
$521
-
kW-mo/yr
-
03 2.7122: Disconnect ballasts $351 - $288
4,503
kWh
$63
-
kW-mo/yr
-
04 4.812: Apply for investment incentives $31,797 $5,000 - - $31,797
TOTAL RECOMMENDED $38,714 $8,100 $5,280
82,508
kWh
$1,637
-
kW-mo/yr
$31,797
TOTAL IMPLEMENTED $38,363 $8,100 $4,992
78,005
kWh
$1,574
-
kW-mo/yr
$31,797
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs