| Assessment Year | 2014 | 
|---|---|
| Principal Product | Bottled Water | 
| NAICS | 312112: Bottled Water Manufacturing | 
| SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters | 
| Sales Range | $10 Mto 50 M | 
| # of Employees | 70 | 
| Plant Area | 377,000 
ft2
 | 
| Annual Production | 19,000,000 
pieces
 | 
| Production Hrs. Annual | 6,396 
hrs
 | 
| Location (State) | Tennessee | 
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $967,251 | 21,554,227 | 
kWh
 | $0.045 | 
| Electricity Demand | $550,280 | 41,893 | 
kW-mo/yr
 | $13.14 | 
| Electricity Fees | $22,763 | - |  | - | 
| Natural Gas | $99,808 | 10,970 | 
MMBtu
 | $9.10 | 
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $115,888 | See individual recommendations below*Non-energy impacts included in savings. | ||
| IMPLEMENTED SAVINGS* | $2,882 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | 
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $107,559 | $235,000 | $5,609 124,645
                                 
kWh
 | - | $10,250 | $91,700 -
                                 
MMBtu
 | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,620 | $2,025 | $1,647 36,594
                                 
kWh
 | $973 -
                                 
kW-mo/yr
 | - | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,827 | $3,000 | $1,777 39,480
                                 
kWh
 | $1,050 -
                                 
kW-mo/yr
 | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,882 | $3,000 | $2,882 64,049
                                 
kWh
 | - | - | - | |
| TOTAL RECOMMENDED | $115,888 | $243,025 | $11,915 264,768
                                 
kWh
 | $2,023 -
                                 
kW-mo/yr
 | $10,250 | $91,700 -
                                 
MMBtu
 | ||
| TOTAL IMPLEMENTED | $2,882 | $3,000 | $2,882 64,049
                                 
kWh
 | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs
             
             
             
            