ITAC Assessment: TT0118
ITAC logo
ITAC Assessment: TT0118
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product hardwood flooring
NAICS 321918: Other Millwork (including Flooring)
SIC 2421: Sawmills and Planing Mills, General
Sales Range $100
M
to 500
M
# of Employees 400
Plant Area 150,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,678
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $735,790 6,551,200
kWh
Electricity Demand $441,302 31,888
kW-mo/yr
Natural Gas $14,004 1,654
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $76,561 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,586

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7135: Install occupancy sensors $534 $125 $534
5,340
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $42,441 $130,082 $42,441
288,769
kWh
-
03 2.4133: Use most efficient type of electric motors $6,125 $2,927 $6,125
46,642
kWh
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $27,461 $800 $21,327
213,272
kWh
$6,134
-
kW-mo/yr
TOTAL RECOMMENDED $76,561 $133,934 $70,427
554,023
kWh
$6,134
-
kW-mo/yr
TOTAL IMPLEMENTED $33,586 $3,727 $27,452
259,914
kWh
$6,134
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs