Assessment Year | 2013 |
---|---|
Principal Product | hardwood flooring |
NAICS | 321918: Other Millwork (including Flooring) |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $100 M to 500M |
# of Employees | 400 |
Plant Area |
150,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,678
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $735,790 | 6,551,200 |
kWh
|
$0.11 |
Electricity Demand | $441,302 | 31,888 |
kW-mo/yr
|
$13.84 |
Natural Gas | $14,004 | 1,654 |
MMBtu
|
$8.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $76,561 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,586 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $534 | $125 |
$534
5,340
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $42,441 | $130,082 |
$42,441
288,769
kWh
|
- | |
03 | 2.4133: Use most efficient type of electric motors | $6,125 | $2,927 |
$6,125
46,642
kWh
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $27,461 | $800 |
$21,327
213,272
kWh
|
$6,134
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $76,561 | $133,934 |
$70,427
554,023
kWh
|
$6,134
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $33,586 | $3,727 |
$27,452
259,914
kWh
|
$6,134
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs