Assessment Year | 2013 |
---|---|
Principal Product | Hydraulic Cylinders |
NAICS | 333611: Turbine and Turbine Generator Set Units Manufacturing |
SIC | 3511: Steam, Gas, and Hydraulic Turbines, and Turbine Generator Set Units |
Sales Range | $5 M to 10M |
# of Employees | 60 |
Plant Area |
42,800
ft2
|
Annual Production | 44,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $76,243 | 785,600 |
kWh
|
$0.097 |
Natural Gas | $17,448 | 1,874 |
MMBtu
|
$9.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,461 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,201 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2314: Replace heat treating oven with more efficient unit | $4,915 | $4,690 |
$(-4,552.0)
(-46,926)
kWh
|
$9,467
-
MMBtu
|
|
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,630 | $2,600 |
$1,630
16,803
kWh
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $145 | $700 |
$145
1,492
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,571 | $25,960 |
$8,571
88,358
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,801 | $5,122 |
$1,801
18,570
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $54 | $394 |
$54
562
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,345 | $15,200 |
$1,345
13,870
kWh
|
- | |
TOTAL RECOMMENDED | $18,461 | $54,666 |
$8,994
92,729
kWh
|
$9,467
-
MMBtu
|
||
TOTAL IMPLEMENTED | $12,201 | $34,776 |
$12,201
125,785
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs