ITAC Assessment: TT0111
ITAC logo
ITAC Assessment: TT0111
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Hardwood Lumber
NAICS 321114: Wood Preservation
SIC 2491: Wood Preserving
Sales Range $5
M
to 10
M
# of Employees 45
Plant Area 500,000
ft2
Annual Production 9,330,241
units
Production Hrs. Annual 8,760
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $241,458 3,546,000
kWh
Electricity Demand $111,367 9,339
kW-mo/yr
Wood $109,244 49,416
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $42,000 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,000

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Wood Savings
01 2.2127: Flash condensate to produce lower pressure steam $6,000 $5,000 - $6,000
-
MMBtu
02 2.2414: Use waste heat from hot flue gases to preheat $17,000 $50,000 - $17,000
-
MMBtu
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $11,000 $5,000 $11,000
119,695
kWh
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,000 $4,000 $7,000
76,170
kWh
-
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,000 $1,500 $1,000
10,881
kWh
-
TOTAL RECOMMENDED $42,000 $65,500 $19,000
206,746
kWh
$23,000
-
MMBtu
TOTAL IMPLEMENTED $19,000 $10,500 $19,000
206,746
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs