Assessment Year | 2013 |
---|---|
Principal Product | N/A |
NAICS | 611310: Colleges, Universities, and Professional Schools |
SIC | 8221: Colleges, Universities, and Professional Schools |
Sales Range | less than $500 k |
# of Employees | 6 |
Plant Area |
6,300
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $39,800 | 497,568 |
kWh
|
$0.080 |
Natural Gas | $439,734 | 109,418 |
MMBtu
|
$4.02 |
Coal | $570,044 | 99,037 |
MMBtu
|
$5.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $385,245 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $373,330 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Coal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1332: Convert combustion equipment to burn natural gas | $362,330 | $650,000 |
$39,800
497,568
kWh
|
- |
$174,000
-
MMBtu
|
$20,530
-
lb
|
$128,000 | |
02 | 2.2442: Preheat combustion air with waste heat | $11,000 | $60,000 | - |
$11,000
-
MMBtu
|
- | - | - | |
03 | 2.2136: Install / repair insulation on steam lines | $11,915 | $11,497 | - |
$11,915
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $385,245 | $721,497 |
$39,800
497,568
kWh
|
$22,915
-
MMBtu
|
$174,000
-
MMBtu
|
$20,530
-
lb
|
$128,000 | ||
TOTAL IMPLEMENTED | $373,330 | $710,000 |
$39,800
497,568
kWh
|
$11,000
-
MMBtu
|
$174,000
-
MMBtu
|
$20,530
-
lb
|
$128,000 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs