ITAC Assessment: TT0089
ITAC logo
ITAC Assessment: TT0089
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Ball and Roller Bearings
NAICS 332991: Ball and Roller Bearing Manufacturing
SIC 3562: Ball and Roller Bearings
Sales Range less than $500
k
# of Employees 13
Plant Area 1,001
ft2
Annual Production 1
units
Production Hrs. Annual 1,500
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $858,303 12,098,790
kWh
Natural Gas $79,600 9,370
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $48,610 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $4,022 $6,293 $7,292
102,845
kWh
$(-3,270.0)
-
MMBtu
02 2.4133: Use most efficient type of electric motors $12,031 $89,180 $12,031
171,878
kWh
-
03 2.9113: Use solar heat for heat $25,369 $109,680 $7,560
108,000
kWh
$17,809
-
MMBtu
04 2.7145: Install skylights $7,188 $96,000 $7,188
79,872
kWh
-
TOTAL RECOMMENDED $48,610 $301,153 $34,071
462,595
kWh
$14,539
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs