Assessment Year | 2012 |
---|---|
Principal Product | Automotive Fuel Tanks |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 300 |
Plant Area |
300,000
ft2
|
Annual Production | 900,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,512,333 | 25,722,000 |
kWh
|
$0.059 |
Electricity Demand | $707,867 | 60,225 |
kW-mo/yr
|
$11.75 |
Electricity Fees | $(-182,028.0) | - |
|
- |
Natural Gas | $33,572 | 3,984 |
MMBtu
|
$8.43 |
LPG | $81,754 | 35,981 |
MMBtu
|
$2.27 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $239,535 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $91,176 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $142,952 | $100,850 | - |
$142,952
-
kW-mo/yr
|
|
02 | 2.4131: Size electric motors for peak operating efficiency | $3,300 | $1,700 |
$3,300
42,800
kWh
|
- | |
03 | 2.4131: Size electric motors for peak operating efficiency | $1,900 | $1,700 |
$1,900
24,500
kWh
|
- | |
04 | 2.6211: Conserve energy by efficient use of vending machines | $207 | $20 |
$207
2,759
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,813 | $8,867 |
$3,111
52,722
kWh
|
$1,702
-
kW-mo/yr
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,203 | $3,940 |
$1,575
26,700
kWh
|
$628
-
kW-mo/yr
|
|
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $421 | $3,440 |
$301
5,100
kWh
|
$120
-
kW-mo/yr
|
|
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $312 | $4,158 |
$223
3,780
kWh
|
$89
-
kW-mo/yr
|
|
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $83,427 | $175,342 |
$59,663
1,011,240
kWh
|
$23,764
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $239,535 | $300,017 |
$70,280
1,169,601
kWh
|
$169,255
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $91,176 | $195,747 |
$64,873
1,099,542
kWh
|
$26,303
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs