| Assessment Year | 2012 |
|---|---|
| Principal Product | Railroad Crossties |
| NAICS | 321114: Wood Preservation |
| SIC | 2491: Wood Preserving |
| Sales Range | $10 M to 50M |
| # of Employees | 55 |
| Plant Area |
72,000
ft2
|
| Annual Production | 1,100,000
pieces
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $167,019 | 3,109,110 |
kWh
|
$0.054 |
| Electricity Demand | $104,051 | 10,612 |
kW-mo/yr
|
$9.81 |
| Electricity Fees | $68,007 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $45,539 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $115 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,296 | $6,000 |
$2,648
34,864
kWh
|
$648
-
kW-mo/yr
|
|
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,912 | $3,000 |
$2,286
33,700
kWh
|
$626
-
kW-mo/yr
|
|
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,245 | $3,500 |
$2,505
39,900
kWh
|
$740
-
kW-mo/yr
|
|
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,391 | $15,000 |
$10,334
164,600
kWh
|
$3,057
-
kW-mo/yr
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,504 | $4,500 |
$4,504
66,437
kWh
|
- | |
| 06 | 2.6211: Conserve energy by efficient use of vending machines | $115 | $10 |
$115
1,226
kWh
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $216 | $2,128 |
$152
2,420
kWh
|
$64
-
kW-mo/yr
|
|
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,819 | $6,000 |
$1,282
20,420
kWh
|
$537
-
kW-mo/yr
|
|
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,757 | $45,510 |
$9,697
154,452
kWh
|
$4,060
-
kW-mo/yr
|
|
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,284 | $6,653 |
$1,610
24,935
kWh
|
$674
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $45,539 | $92,301 |
$35,133
542,954
kWh
|
$10,406
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $115 | $10 |
$115
1,226
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs