Assessment Year | 2011 |
---|---|
Principal Product | Practice Bomb Shells |
NAICS | 333517: Machine Tool Manufacturing |
SIC | 3541: Machine Tools, Metal Cutting Types |
Sales Range | $500 k to 1M |
# of Employees | 142 |
Plant Area |
82,000
ft2
|
Annual Production | 0
pieces
|
Production Hrs. Annual | 2,750
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $91,675 | 1,510,200 |
kWh
|
$0.061 |
Electricity Demand | $90,883 | 7,199 |
kW-mo/yr
|
$12.62 |
Natural Gas | $66,480 | 8,220 |
MMBtu
|
$8.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,319 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,520 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $9,142 | $15,000 |
$9,142
-
kW-mo/yr
|
- | - | |
02 | 2.7145: Install skylights | $2,883 | $36,500 | - | $2,883 | - | |
03 | 2.8113: Purchase gas directly from a contract gas supplier | $14,378 | $1,200 | - | - |
$14,378
-
MMBtu
|
|
04 | 2.7243: Improve air circulation with destratification fans / other methods | $337 | $29,076 | - | $337 | - | |
05 | 2.4133: Use most efficient type of electric motors | $267 | $1,370 | - | $267 | - | |
06 | 2.3511: Use plant owned transformers or lease transformers | $5,312 | $3,825 | - | $5,312 | - | |
TOTAL RECOMMENDED | $32,319 | $86,971 |
$9,142
-
kW-mo/yr
|
$8,799 |
$14,378
-
MMBtu
|
||
TOTAL IMPLEMENTED | $23,520 | $16,200 |
$9,142
-
kW-mo/yr
|
- |
$14,378
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs