ITAC Assessment: TT0081
ITAC logo
ITAC Assessment: TT0081
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Beverage Alcohol
NAICS 312140: Distilleries
SIC 2085: Distilled and Blended Liquors
Sales Range greater than $500
M
# of Employees 370
Plant Area 1,000,000
ft2
Annual Production 23,772
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,958,100 38,838,000
kWh
Electricity Demand $978,432 72,073
kW-mo/yr
Electricity Fees $47,830 -
Natural Gas $198,719 31,795
MMBtu
Wood $2,728,028 1,032,051
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $413,458 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $100,466

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Wood Savings
01 2.1113: Reduce combustion air flow to optimum $89,000 $24,500 - - $89,000
-
MMBtu
02 2.3321: Use steam pressure reduction to generate power $204,112 $553,850 $212,025
3,723,000
kWh
$63,087
-
kW-mo/yr
$(-71,000.0)
-
MMBtu
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $18,218 $44,000 $11,507
202,062
kWh
$6,711
-
kW-mo/yr
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $1,662 $5 $1,662
22,490
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $58,700 $103,900 $42,030
737,950
kWh
$16,670
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $34,694 $70,320 $26,150
459,300
kWh
$8,544
-
kW-mo/yr
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,492 $8,160 $1,880
33,050
kWh
$612
-
kW-mo/yr
-
08 2.7142: Utilize higher efficiency lamps and/or ballasts $4,580 $22,680 $3,290
57,800
kWh
$1,290
-
kW-mo/yr
-
TOTAL RECOMMENDED $413,458 $827,415 $298,544
5,235,652
kWh
$96,914
-
kW-mo/yr
$18,000
-
MMBtu
TOTAL IMPLEMENTED $100,466 $205,060 $73,350
1,288,100
kWh
$27,116
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Wood Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs