Assessment Year | 2011 |
---|---|
Principal Product | HVAC Coils |
NAICS | 332996: Fabricated Pipe and Pipe Fitting Manufacturing |
SIC | 3498: Fabricated Pipe and Pipe Fittings |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
68,000
ft2
|
Annual Production | 15,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $60,470 | 1,015,920 |
kWh
|
$0.060 |
Electricity Demand | $26,841 | 3,090 |
kW-mo/yr
|
$8.69 |
Electricity Fees | $1,668 | - |
|
- |
Natural Gas | $8,230 | 1,146 |
MMBtu
|
$7.18 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,656 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $1,768 | - |
$1,768
19,968
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,271 | $3,600 |
$3,271
36,940
kWh
|
- | |
03 | 2.7241: Install outside air damper / economizer on hvac unit | $549 | $600 |
$549
6,200
kWh
|
- | |
04 | 2.3212: Optimize plant power factor | $985 | $1,980 | - | $985 | |
05 | 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings | $2,083 | $4,900 |
$2,083
23,528
kWh
|
- | |
TOTAL RECOMMENDED | $8,656 | $11,080 |
$7,671
86,636
kWh
|
$985 | ||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs