| Assessment Year | 2011 |
|---|---|
| Principal Product | Automotive Parts |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | less than $500 k |
| # of Employees | 547 |
| Plant Area |
340,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,681,493 | 43,116,606 |
kWh
|
$0.039 |
| Electricity Demand | $1,021,757 | 87,249 |
kW-mo/yr
|
$11.71 |
| Electricity Fees | $59,962 | - |
|
- |
| Natural Gas | $594,549 | 70,368 |
MMBtu
|
$8.45 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $183,000 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $90,490 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,010 | $5,000 |
$1,610
43,877
kWh
|
$1,500
-
kW-mo/yr
|
- | $(-100.0) | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,300 | $32,200 |
$9,700
264,999
kWh
|
$5,300
-
kW-mo/yr
|
- | $3,300 | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $39,600 | $109,700 |
$24,500
667,940
kWh
|
$13,500
-
kW-mo/yr
|
- | $1,600 | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,200 | $3,700 |
$600
16,106
kWh
|
$300
-
kW-mo/yr
|
- | $300 | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,000 | $12,200 |
$6,000
112,703
kWh
|
- | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $18,990 | $5,000 |
$18,990
517,361
kWh
|
- | - | - | |
| 07 | 2.2437: Recover waste heat from equipment | $9,600 | $10,000 | - | - |
$9,600
-
MMBtu
|
- | |
| 08 | 2.2625: Chill water to the highest temperature possible | $20,800 | $22,000 |
$20,800
382,032
kWh
|
- | - | - | |
| 09 | 2.2511: Insulate bare equipment | $65,500 | $61,500 |
$43,700
1,189,855
kWh
|
$21,800
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $183,000 | $261,300 |
$125,900
3,194,873
kWh
|
$42,400
-
kW-mo/yr
|
$9,600
-
MMBtu
|
$5,100 | ||
| TOTAL IMPLEMENTED | $90,490 | $78,700 |
$68,690
1,819,919
kWh
|
$21,800
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs