Assessment Year | 2011 |
---|---|
Principal Product | Water Heater Components |
NAICS | 332119: Metal Crown, Closure, and Other Metal Stamping (except Automotive) |
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 70 |
Plant Area |
55,440
ft2
|
Annual Production | 70,000,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $223,149 | 4,203,360 |
kWh
|
$0.053 |
Electricity Demand | $114,783 | 8,544 |
kW-mo/yr
|
$13.43 |
Electricity Fees | $6,360 | - |
|
- |
Natural Gas | $83,727 | 8,618 |
MMBtu
|
$9.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $76,915 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $76,915 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,600 | $2,500 |
$1,100
21,326
kWh
|
$500
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,400 | $26,700 |
$5,700
105,057
kWh
|
$2,300
-
kW-mo/yr
|
$1,400 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $957 | $4,000 |
$557
10,320
kWh
|
$400
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $414 | $3,200 |
$300
5,219
kWh
|
$114
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,844 | $29,100 |
$1,300
24,935
kWh
|
$544
-
kW-mo/yr
|
- | |
06 | 2.3212: Optimize plant power factor | $7,300 | $8,500 | - |
$7,300
-
kW-mo/yr
|
- | |
07 | 2.4239: Eliminate or reduce compressed air usage | $37,600 | $5,500 |
$27,400
507,306
kWh
|
$10,200
-
kW-mo/yr
|
- | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,800 | $5,000 |
$17,800
329,928
kWh
|
- | - | |
TOTAL RECOMMENDED | $76,915 | $84,500 |
$54,157
1,004,091
kWh
|
$21,358
-
kW-mo/yr
|
$1,400 | ||
TOTAL IMPLEMENTED | $76,915 | $84,500 |
$54,157
1,004,091
kWh
|
$21,358
-
kW-mo/yr
|
$1,400 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs