ITAC Assessment: TT0062
ITAC logo
ITAC Assessment: TT0062
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Chlorine and Caustic Soda
NAICS 325180: Other Basic Inorganic Chemical Manufacturing
SIC 2812: Alkalies and Chlorine
Sales Range greater than $500
M
# of Employees 208
Plant Area 1,306,800
ft2
Annual Production 300,000
ton
Production Hrs. Annual 8,760
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $26,187,224 832,501,039
kWh
Electricity Demand $10,641,962 1,234,728
kW-mo/yr
Electricity Fees $(-241,953.0) -
Natural Gas $1,428,562 252,458
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $374,100 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $187,100

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $33,700 $60,600 $32,100
606,104
kWh
- $1,600
02 2.7142: Utilize higher efficiency lamps and/or ballasts $10,900 $36,300 $8,400
158,722
kWh
- $2,500
03 2.7142: Utilize higher efficiency lamps and/or ballasts $8,100 $6,300 $4,400
84,630
kWh
- $3,700
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,600 $4,200 $2,400
45,990
kWh
- $200
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,000 $1,500 $1,900
36,792
kWh
- $100
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $37,800 $26,000 $37,800
714,733
kWh
- -
07 2.4231: Reduce the pressure of compressed air to the minimum required $13,400 $10,000 $13,400
253,750
kWh
- -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $45,100 $4,900 $45,100
851,568
kWh
- -
09 2.2628: Utilize a less expensive cooling method $23,000 $50,000 $23,000
434,846
kWh
- -
10 2.1113: Reduce combustion air flow to optimum $84,900 $45,000 $17,900
338,003
kWh
$67,000
-
MMBtu
-
11 2.1124: Replace direct fired with steam heat $78,600 $30,000 - $78,600
-
MMBtu
-
12 2.1213: Direct warmest air to combustion intake $34,000 $30,000 - $34,000
-
MMBtu
-
TOTAL RECOMMENDED $374,100 $304,800 $186,400
3,525,138
kWh
$179,600
-
MMBtu
$8,100
TOTAL IMPLEMENTED $187,100 $174,900 $100,400
1,900,721
kWh
$78,600
-
MMBtu
$8,100
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs