| Assessment Year | 2010 |
|---|---|
| Principal Product | Medium Voltage Switchgear |
| NAICS | 335311: Power, Distribution, and Specialty Transformer Manufacturing |
| SIC | 3612: Power, Distribution, and Specialty Transformers |
| Sales Range | $100 M to 500M |
| # of Employees | 300 |
| Plant Area |
200,000
ft2
|
| Annual Production | 6,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Tennessee |
| View Case Study | |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $196,354 | 5,041,186 |
kWh
|
$0.039 |
| Electricity Demand | $205,883 | 13,235 |
kW-mo/yr
|
$15.56 |
| Natural Gas | $133,487 | 17,571 |
MMBtu
|
$7.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,244 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,444 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,444 | $3,000 |
$7,843
201,360
kWh
|
$5,602
-
kW-mo/yr
|
- | |
| 02 | 2.2437: Recover waste heat from equipment | $4,100 | $7,000 | - | - |
$4,100
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,000 | $15,450 |
$4,100
104,664
kWh
|
$2,900
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,700 | $15,000 |
$1,350
34,830
kWh
|
$1,350
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $27,244 | $40,450 |
$13,293
340,854
kWh
|
$9,852
-
kW-mo/yr
|
$4,100
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $13,444 | $3,000 |
$7,843
201,360
kWh
|
$5,602
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs