| Assessment Year | 2010 |
|---|---|
| Principal Product | steel stamping |
| NAICS | 336370: Motor Vehicle Metal Stamping |
| SIC | 3465: Automotive Stampings |
| Sales Range | $100 M to 500M |
| # of Employees | 322 |
| Plant Area |
680,000
ft2
|
| Annual Production | 29,641,500
pieces
|
| Production Hrs. Annual | 4,750
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $586,727 | 14,510,000 |
kWh
|
$0.040 |
| Electricity Demand | $504,029 | 37,453 |
kW-mo/yr
|
$13.46 |
| Electricity Fees | $65,618 | - |
|
- |
| Natural Gas | $77,136 | 5,901 |
MMBtu
|
$13.07 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $211,800 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $56,000 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $56,000 | $1,000 |
$24,500
766,400
kWh
|
$31,500
-
kW-mo/yr
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $97,000 | $421,000 |
$35,400
1,105,800
kWh
|
$36,400
-
kW-mo/yr
|
- | $25,200 | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $35,900 | $91,150 |
$16,000
498,750
kWh
|
$16,400
-
kW-mo/yr
|
$3,500 | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $18,500 | $4,500 |
$18,500
579,300
kWh
|
- | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,400 | $4,500 |
$4,400
134,900
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $211,800 | $522,150 |
$98,800
3,085,150
kWh
|
$84,300
-
kW-mo/yr
|
$3,500 | $25,200 | ||
| TOTAL IMPLEMENTED | $56,000 | $1,000 |
$24,500
766,400
kWh
|
$31,500
-
kW-mo/yr
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs