ITAC Assessment: TT0048
ITAC logo
ITAC Assessment: TT0048
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product steel stamping
NAICS 336370: Motor Vehicle Metal Stamping
SIC 3465: Automotive Stampings
Sales Range $100
M
to 500
M
# of Employees 322
Plant Area 680,000
ft2
Annual Production 29,641,500
pieces
Production Hrs. Annual 4,750
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $586,727 14,510,000
kWh
Electricity Demand $504,029 37,453
kW-mo/yr
Electricity Fees $65,618 -
Natural Gas $77,136 5,901
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $211,800 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $56,000

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4322: Use or replace with energy efficient substitutes $56,000 $1,000 $24,500
766,400
kWh
$31,500
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $97,000 $421,000 $35,400
1,105,800
kWh
$36,400
-
kW-mo/yr
- $25,200
03 2.7142: Utilize higher efficiency lamps and/or ballasts $35,900 $91,150 $16,000
498,750
kWh
$16,400
-
kW-mo/yr
$3,500 -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $18,500 $4,500 $18,500
579,300
kWh
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,400 $4,500 $4,400
134,900
kWh
- - -
TOTAL RECOMMENDED $211,800 $522,150 $98,800
3,085,150
kWh
$84,300
-
kW-mo/yr
$3,500 $25,200
TOTAL IMPLEMENTED $56,000 $1,000 $24,500
766,400
kWh
$31,500
-
kW-mo/yr
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs