| Assessment Year | 2009 |
|---|---|
| Principal Product | Frozen Dough |
| NAICS | 311412: Frozen Specialty Food Manufacturing |
| SIC | 2038: Frozen Specialties, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 350 |
| Plant Area |
250,000
ft2
|
| Annual Production | 257,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,835,656 | 37,759,800 |
kWh
|
$0.049 |
| Electricity Demand | $937,961 | 83,153 |
kW-mo/yr
|
$11.28 |
| Electricity Fees | $43,810 | - |
|
- |
| LPG | $183,962 | 15,565 |
MMBtu
|
$11.82 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $90,808 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $45,883 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7221: Lower temperature during the winter season and vice-versa | $1,330 | - |
$1,330
16,620
kWh
|
- | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $25,865 | - |
$18,975
254,305
kWh
|
$6,890
-
kW-mo/yr
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $31,503 | - |
$23,126
310,000
kWh
|
$8,377
-
kW-mo/yr
|
|
| 04 | 2.4131: Size electric motors for peak operating efficiency | $9,530 | - |
$9,530
148,284
kWh
|
- | |
| 05 | 2.4131: Size electric motors for peak operating efficiency | $9,530 | - |
$9,530
148,284
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,050 | - |
$8,730
279,130
kWh
|
$4,320
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $90,808 | - |
$71,221
1,156,623
kWh
|
$19,587
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $45,883 | - |
$33,186
605,750
kWh
|
$12,697
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs