ITAC Assessment: TT0040
ITAC logo
ITAC Assessment: TT0040
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Mounted Ball Bearings
NAICS 332991: Ball and Roller Bearing Manufacturing
SIC 3562: Ball and Roller Bearings
Sales Range less than $500
k
# of Employees 220
Plant Area 200,000
ft2
Annual Production 1
units
Production Hrs. Annual 6,000
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,383,097 19,965,600
kWh
Natural Gas $105,766 7,098
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $245,298 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $114,948

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $88,970 $217,270 $47,140
1,012,860
kWh
$23,620
-
kW-mo/yr
$18,210
02 2.7142: Utilize higher efficiency lamps and/or ballasts $9,100 $32,390 $4,700
101,106
kWh
$2,360
-
kW-mo/yr
$2,040
03 2.4322: Use or replace with energy efficient substitutes $24,648 - $18
407,100
kWh
$24,630
-
kW-mo/yr
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $30,600 - $20,385
438,000
kWh
$10,215
-
kW-mo/yr
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $8,450 $800 $5,630
120,900
kWh
$2,820
-
kW-mo/yr
-
06 2.7221: Lower temperature during the winter season and vice-versa $39,750 - $39,750
854,104
kWh
- -
07 2.7496: Install partitions to reduce size of conditioned space $32,280 $40,000 $32,280
693,597
kWh
- -
08 2.7224: Reduce space conditioning during non-working hours $9,000 - $9,000
193,382
kWh
- -
09 2.7224: Reduce space conditioning during non-working hours $2,500 - $2,500
53,717
kWh
- -
TOTAL RECOMMENDED $245,298 $290,460 $161,403
3,874,766
kWh
$63,645
-
kW-mo/yr
$20,250
TOTAL IMPLEMENTED $114,948 $800 $77,283
2,067,203
kWh
$37,665
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs