Assessment Year | 2009 |
---|---|
Principal Product | Valves |
NAICS | 336310: Motor Vehicle Gasoline Engine and Engine Parts Manufacturing |
SIC | 3592: Carburetors, Pistons, Piston Rings, and Valves |
Sales Range | $50 M to 100M |
# of Employees | 270 |
Plant Area |
172,000
ft2
|
Annual Production | 50,000,000
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,691,560 | 25,740,360 |
kWh
|
$0.066 |
Natural Gas | $406,830 | 23,068 |
MMBtu
|
$17.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $245,820 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $115,810 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $2,163 | $16,183 |
$2,163
32,784
kWh
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $1 | - |
$1
1
kWh
|
- | - | |
03 | 2.4235: Remove or close off unneeded compressed air lines | $77,380 | $7,000 |
$77,380
1,230,900
kWh
|
- | - | |
04 | 2.4234: Cool compressor air intake with heat exchanger | $36,266 | $12,000 |
$36,266
614,685
kWh
|
- | - | |
05 | 2.1116: Improve combustion control capability | $112,568 | $64,000 | - | - |
$112,568
-
MMBtu
|
|
06 | 2.8121: Apply for tax-free status for energy purchases | $6,012 | $250 | - | - |
$6,012
-
MMBtu
|
|
07 | 2.3212: Optimize plant power factor | $11,430 | $13,000 | - |
$11,430
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $245,820 | $112,433 |
$115,810
1,878,370
kWh
|
$11,430
-
kW-mo/yr
|
$118,580
-
MMBtu
|
||
TOTAL IMPLEMENTED | $115,810 | $35,183 |
$115,810
1,878,370
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs