Assessment Year | 2008 |
---|---|
Principal Product | Condensed Milk |
NAICS | 311514: Dry, Condensed, and Evaporated Dairy Product Manufacturing |
SIC | 2023: Dry, Condensed, and Evaporated Dairy Products |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
158,750
ft2
|
Annual Production | 31,593
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $291,631 | 6,272,880 |
kWh
|
$0.046 |
Electricity Demand | $131,662 | 12,617 |
kW-mo/yr
|
$10.44 |
Electricity Fees | $2,762 | - |
|
- |
Natural Gas | $1,408,583 | 182,263 |
MMBtu
|
$7.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $188,996 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $119,925 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,401 | $13,400 |
$14,360
206,035
kWh
|
$3,378
-
kW-mo/yr
|
- | $3,663 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,785 | $23,530 |
$12,600
180,806
kWh
|
$2,970
-
kW-mo/yr
|
- | $3,215 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,700 | $11,100 |
$6,790
97,455
kWh
|
$1,600
-
kW-mo/yr
|
- | $1,310 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,685 | $7,344 |
$2,400
34,532
kWh
|
$575
-
kW-mo/yr
|
- | $710 | |
05 | 2.2135: Repair and eliminate steam leaks | $55,100 | $20,000 | - | - |
$55,100
-
MMBtu
|
- | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $37,200 | $1,000 | - | - |
$37,200
-
MMBtu
|
- | |
07 | 2.2136: Install / repair insulation on steam lines | $13,600 | $8,310 | - | - |
$13,600
-
MMBtu
|
- | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,275 | $4,900 |
$12,275
194,706
kWh
|
- | - | - | |
09 | 2.2113: Repair or replace steam traps | $1,750 | $1,600 |
$1,750
25,065
kWh
|
- | - | - | |
10 | 2.3212: Optimize plant power factor | $15,500 | $32,800 | - | - | - | $15,500 | |
TOTAL RECOMMENDED | $188,996 | $123,984 |
$50,175
738,599
kWh
|
$8,523
-
kW-mo/yr
|
$105,900
-
MMBtu
|
$24,398 | ||
TOTAL IMPLEMENTED | $119,925 | $35,810 |
$14,025
219,771
kWh
|
- |
$105,900
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs