Assessment Year | 1984 |
---|---|
Principal Product | SPUN METAL PARTS |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | n/a |
# of Employees | 72 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $38,092 | 428,488 |
kWh
|
$0.089 |
Natural Gas | $25,778 | 4,609 |
MMBtu
|
$5.59 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,595 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,455 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,951 | $16,300 |
$10,056
139,215
kWh
|
$(-105.0)
-
MMBtu
|
|
02 | 2.7492: Use proper thickness of insulation on building envelope | $14,140 | $29,400 | - |
$14,140
-
MMBtu
|
|
03 | 2.2212: Use minimum safe oven ventilation | $335 | $300 | - |
$335
-
MMBtu
|
|
04 | 2.7492: Use proper thickness of insulation on building envelope | $169 | $200 |
$169
2,052
kWh
|
- | |
TOTAL RECOMMENDED | $24,595 | $46,200 |
$10,225
141,267
kWh
|
$14,370
-
MMBtu
|
||
TOTAL IMPLEMENTED | $10,455 | $16,800 |
$10,225
141,267
kWh
|
$230
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs