ITAC Assessment: TR0038
ITAC logo
ITAC Assessment: TR0038
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Water
NAICS 221310: Water Supply and Irrigation Systems
SIC 4941: Water Supply
Sales Range $1
M
to 5
M
# of Employees 2
Plant Area 16,723,737
ft2
Annual Production 220,000
Tgal
Production Hrs. Annual 5,840
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $17,781 409,680
kWh
Electricity Demand $15,908 1,385
kW-mo/yr
Electricity Fees $406 -
Waste Disposal Costs
Water Usage $49,500 220,000
Tgal
TOTAL YEARLY COSTS $83,595
RECOMMENDED SAVINGS* $2,026 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,357

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $337 $921 $337
7,830
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $303 $583 $303
7,054
kWh
- -
03 2.7135: Install occupancy sensors $251 $195 $251
5,827
kWh
- -
04 3.7311: Maintain machines to reduce leaks $717 $884 - $4 $712
05 2.7232: Replace existing hvac unit with high efficiency model $419 $4,300 $419
9,738
kWh
- -
TOTAL RECOMMENDED $2,026 $6,883 $1,309
30,450
kWh
$4 $712
TOTAL IMPLEMENTED $1,357 $2,388 $640
14,884
kWh
$4 $712
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs