ITAC Assessment: TR0025
ITAC logo
ITAC Assessment: TR0025
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Aloe Vera juice and concentrates
NAICS 325611: Soap and Other Detergent Manufacturing
SIC 2844: Perfumes, Cosmetics, and Other Toilet Preparations
Sales Range $1
M
to 5
M
# of Employees 50
Plant Area 71,515
ft2
Annual Production 1,509
ton
Production Hrs. Annual 2,900
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $130,422 1,549,720
kWh
Electricity Demand $47,732 4,567
kW-mo/yr
Electricity Fees $346 -
Natural Gas $17,906 2,863
MMBtu
Waste Disposal Costs
Water Usage $40,359 7,030
Tgal
TOTAL YEARLY COSTS $236,765
RECOMMENDED SAVINGS* $11,601 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,601

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings
01 2.2511: Insulate bare equipment $657 $440 $657
7,830
kWh
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,326 $1,145 $878
10,471
kWh
$448
-
kW-mo/yr
- -
03 2.2515: Use optimum thickness insulation $1,067 $830 - - $1,067
-
MMBtu
-
04 2.2135: Repair and eliminate steam leaks $1,683 $130 $3
33
kWh
- $27
-
MMBtu
$1,653
-
Tgal
05 2.7135: Install occupancy sensors $371 $676 $371
4,420
kWh
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $6,497 $9,060 $4,302
51,295
kWh
$2,195
-
kW-mo/yr
- -
TOTAL RECOMMENDED $11,601 $12,281 $6,210
74,049
kWh
$2,643
-
kW-mo/yr
$1,095
-
MMBtu
$1,653
-
Tgal
TOTAL IMPLEMENTED $11,601 $12,281 $6,210
74,049
kWh
$2,643
-
kW-mo/yr
$1,095
-
MMBtu
$1,653
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs