| Assessment Year | 2019 |
|---|---|
| Principal Product | Sewarage treatment |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $1 M to 5M |
| # of Employees | 6 |
| Plant Area |
994,816
ft2
|
| Annual Production | 1,916,250
Tgal
|
| Production Hrs. Annual | 8,544
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $138,061 | 3,487,440 |
kWh
|
$0.040 |
| Electricity Demand | $76,947 | 7,420 |
kW-mo/yr
|
$10.37 |
| Electricity Fees | $6,483 | - |
|
- |
| TOTAL YEARLY COSTS | $221,491 | |||
| RECOMMENDED SAVINGS* | $25,656 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,991 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3191: Use demand controller or load shedder | $11,196 | $14,000 | - |
$11,196
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,055 | $1,825 |
$2,231
56,493
kWh
|
$823
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,937 | $6,050 |
$2,841
71,916
kWh
|
$2,096
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,038 | $308 |
$132
3,336
kWh
|
$47
-
kW-mo/yr
|
$858 | |
| 05 | 2.4311: Recover mechanical energy | $5,431 | $25,000 |
$5,431
137,493
kWh
|
- | - | |
| TOTAL RECOMMENDED | $25,656 | $47,183 |
$10,635
269,238
kWh
|
$14,163
-
kW-mo/yr
|
$858 | ||
| TOTAL IMPLEMENTED | $7,991 | $7,875 |
$5,072
128,409
kWh
|
$2,919
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs